Dar Al Noor Expansion Project

Phase 1 Construction Updates

Community updates on the Phase 1 parking lot, most recent first

Site Work Update · September 2026

Alhamdulillah, we want to share a clear update on the Phase 1 site work for the Dar Al Noor / MAV Expansion Project. The project remains active and under management. At the same time, the heavy field work is currently paused while a few important items are finalized. We know delays are frustrating, especially when the community is eager to see visible progress, so we want to explain where things stand in plain language.

Where things stand today

  • The underground StormTech chambers have been delivered and are on site.
  • The related storm structures have been ordered, but fabrication is waiting on final approved engineering details and structure heights.
  • Survey staking and layout work are waiting on final signed/stamped civil plans from Prince William County.
  • The site team is also working through the soil and clay findings so the next phase of work can be planned correctly.

Why the restart is waiting

The revised civil/site plans are still awaiting final County signature and stamped release. We have continued to see progress on the revision, but several construction steps cannot responsibly move forward until the final approved plans are issued. Previous revision timeline commitments and cost-savings shared with the construction committee were inaccurate.

This matters because the revised plans affect exact elevations, utility locations, stormwater structure heights, and other details that the field team must build from. Starting heavy work before those details are final could create rework, inspection issues, and unnecessary cost.

The Construction Committee is taking the careful approach: move forward when the plans, quantities, and field layout are ready, rather than forcing work ahead of final approvals.

Soil and clay assessment

During site operations, the team identified unsuitable clay and mixed debris in the work area. This material cannot be used as structural fill or compaction material under the future parking lot and site improvements.

The current planning estimate is more than 500 truckloads of unsuitable material. Based on an estimated hauling cost of approximately $310 per truckload, the potential exposure is at least approximately $155,000. This is an unexpected and unbudgeted item and has not yet been paid.

Over the next one to two weeks, the team is working to finalize the cut/fill quantification, compare hauling and disposal options, and select the most cost-effective removal path, inshaAllah.

Updated timeline

Because final County release and soil quantification are still pending, the original December completion target is now under review. The current high-level path is below.

TimingWhat we expect to happen
Now – mid SeptemberContinue County follow-up, finalize soil quantification planning, and complete shed relocation planning.
Next 1–2 weeksConfirm contractor pricing and the best hauling/disposal approach for unsuitable soil and debris.
Late September / OctoberAfter final plan release, remobilize surveyors for staking, begin bad-soil removal, and release storm-structure fabrication.
October / NovemberResume heavy site work, including stormwater installation, mass grading, and compaction as approvals, materials, and field conditions allow.
Late 2026 / Q1 2027Resequence curb/gutter, electrical bases, stone subbase, and asphalt once the remaining dependencies are better defined.
September 2026 Community Update cover slide for the Dar Al Noor Expansion Project, Phase 1 Site Work.Where things stand today slide showing current Phase 1 status and site work.Why the restart is waiting slide showing County plan release, storm structure details, and soil or clay quantity.Soil assessment update slide describing unsuitable clay, mixed debris, truckloads, hauling estimate, and potential exposure.Updated timeline slide showing the current high-level restart path from late September through Q1 2027.Funding status and next steps slide showing expansion funds summary, changed spending, and upcoming actions.

Community update slide 1 of 6

Funding status

For transparency, below is the current community-level funding view. These figures are approximate and for community update purposes; final Treasurer/accounting records remain controlling.

Approximate funds raised

$4,375,000

Approximate spent to date

$1,983,685

Approximate cash on hand

$2,391,315

Known added spend since June baseline

$553,685

Estimated soil/debris removal exposure

$155,000+ estimated / not yet paid

All figures are approximate and for community update purposes; final Treasurer/accounting records remain controlling.

What the community should know

The current pause is tied to County plan-release timing, final engineering details, and soil conditions that must be quantified before heavy field work can responsibly restart.

The Construction Committee is actively managing the process with the site supervisor, engineers, surveyors, and contractors.

Our priority is to protect donated funds, avoid avoidable rework, maintain safety, and move the project forward correctly once the required approvals and field information are in place.

Safety reminder

Please continue to avoid construction areas, equipment, markings, materials, and soil piles on site. For everyone’s safety, children should not enter or play near the construction area.

JazakumAllahu khairan for your continued duas, patience, generosity, and support. We will continue to share official updates through MAV / Dar Al Noor communication channels as milestones are completed.

MAV Administration & Construction Committee

Official September 2026 documents

Parking Lot Update · July 25, 2026

Alhamdulillah, we are pleased to share the July 2026 community update on the Dar Al Noor / MAV Expansion Project Phase 1 site-development work.

Site work continues to progress. Titan Company completed brush-debris clearing during June, and a significant portion of the topsoil mitigation, removal, and haul-off has now been completed. Remaining soil cleanup and grading/footprint preparation are continuing as the team prepares the site for the next stormwater installation sequence.

On the materials side, the underground StormTech chambers have been successfully delivered to the site. The related storm structures have also been ordered; however, fabrication of those structures is waiting on the final approved and stamped engineering plans. Prince William County approval of the revised plan is pending, and we are now awaiting the final County signature and stamped issuance.

The Phase 1 revision helps finalize the drainage and stormwater details that must be built underground before the parking lot can be completed. The final County signature confirms the exact approved configuration, which allows custom stormwater structures to be manufactured and installed correctly.

During ongoing site work, the team identified unsuitable material with high clay content and mixed debris. The site inspector verified that this material cannot be reused anywhere in the project, and supporting reports identify areas with up to approximately four feet of unsuitable clay depth. The current estimate is more than 500 truckloads of unusable soil and debris requiring off-site disposal.

While this creates a significant logistics challenge and takes up valuable workspace on site, removing this material is the right construction decision. Proper disposal protects the long-term quality of the parking lot, supports proper compaction, helps preserve drainage performance, and reduces the risk of future pavement or settlement issues. The project team is reviewing cost-effective hauling and dumping options so this work can proceed responsibly. We are requesting the community to donate generously to cover this unexpected cost.

Recent Phase 1 Expenditure Update

Since the last community update, the following July-reported Phase 1 payments have been made for previously approved project work and materials.

CategoryAmountPurpose
Titan Site Group$65,000.00Topsoil haul-off and related site-work progress
E&S contractor$40,000.00Erosion controls, inlet protection, and super silt fence work
StormTech system allocation$435,685.28Special-order stormwater infrastructure allocation
Total July-reported payments$540,685.28Current-cycle reported Phase 1 payments

All figures are approximate and provided for community update purposes. Final accounting and cash balances remain subject to Treasurer confirmation.

What Happens Next

  • Receive final County signature and stamped plan issuance.
  • Release storm structure fabrication once approved engineering plans are available.
  • Continue remaining soil cleanup, grading, and footprint preparation.
  • Select the most cost-effective hauling and disposal path for unsuitable soil and debris.
  • Maintain erosion and sediment controls, inspection readiness, and safe access around active work areas.
  • Prepare the site for the next stormwater installation sequence.

Community safety reminder

Please stay cautious

As construction activity continues, please remain cautious around work areas, construction equipment, soil stockpiles, delivery areas, flags, markings, and posted signs. Keep children away from active construction areas and follow any direction provided by MAV staff or the construction team.

We are grateful to Allah SWT and to our community for your continued support, patience, duas, and generosity as this important phase of the expansion continues to move forward.

JazakumAllahu khairan for your continued support and duas.

MAV Administration & Construction Team

Parking Lot Update · June 1, 2026

Alhamdulillah, we are pleased to share another positive update on the Dar Al Noor / MAV Expansion Project Phase 1 parking lot construction.

Site work continues to move forward steadily, and we remain on track. Our site contractor, Titan Company, continues to perform well. All trees in the designated work area have now been removed, and the remaining brush debris is expected to be cleared within approximately one week. Once this work is complete, the next major step will be soil cleanup and removal.

After coordination with the contractor, we have been informed that the soil removal work is expected to be completed by the end of June, insha’Allah. This would place this portion of the project approximately one month ahead of schedule.

In parallel with the site work, our engineering firm submitted the revised site plan to the County on Friday, May 29. We are now awaiting the County’s response and are hopeful for prompt and positive feedback so that we can move forward with the next stage of material ordering. Some of the required storm-water chambers and related structures are special-order items and cannot be returned once ordered, so we are working carefully to ensure proper approvals and coordination before placing those orders.

Since our last update, an additional $142,000 has been spent on completed project work. We are grateful to Allah SWT and to our community for your continued support, patience, and generosity as this important phase of the expansion continues to progress.

As construction activity continues, please remain cautious around the work areas, equipment, markings, and any posted signs. For everyone’s safety, we ask community members and families to continue keeping children away from active construction areas.

We will continue to keep the community updated as the project advances. JazakumAllahu khairan for your continued support and duas.

MAV Administration & Construction Team

Parking Lot Update · May 15, 2026

Site preparation and land clearing work is currently underway for the Dar Al Noor Phase 1 parking lot expansion project (see pictures below). Heavy construction equipment is actively being used to clear trees, remove brush, and level the ground in preparation for the new parking area. The work includes excavation, grading, and removal of tree stumps and debris to create a stable foundation for future paving and infrastructure development.

The expanded parking lot will help improve accessibility, increase parking capacity for community members and visitors, and support the continued growth of Dar Al Noor’s programs and activities. Despite the weather conditions, construction crews are making steady progress to prepare the site for the next phase of development. Alhamdulillah.

Parking Lot Update · May 7, 2026

Alhamdulillah, survey and stakeout work has started today for the MAV Expansion Project Phase 1, including markings for tree clearing and initial grading.

You may notice flags, stakes, paint markings, or other survey markers around the property. These markings are important for construction accuracy and County compliance. Please do not touch, move, remove, or interfere with any markings, flags, stakes, equipment, or work crews on site.

For everyone’s safety, please also keep children away from marked areas and follow any posted signs or directions from MAV staff, volunteers, or contractors.

JazakumAllahu khairan for your cooperation as we begin this important phase of the expansion project.

MAV Administration & Construction Team